DOWNLOAD the newest PracticeVCE PK0-004 PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1G8niZhzlguSDaBbbml9IHvXbkbhwyi2R First of all, we have the best and most first-class operating system, in addition, we also solemnly assure users that users can receive the information from the PK0-004 learning material within 5-10 minutes after their payment. Second, once we have written the latest version of the PK0-004 learning material, our products will send them the latest version of the PK0-004 Training Material free of charge for one year after the user buys the product. Last but not least, our perfect customer service staff will provide users with the highest quality and satisfaction in the hours.

Skills Outline

The CompTIA PK0-004 exam equips you with fundamental project management skills, including negotiation, managing expectations, conflict resolution, communication, as well as team building. The content of the certification test revolves around four domains that cover specific PM skills. Let’s have a closer look at what each topic area contains.

  • Communication & Change Management (26%)This topic includes using the relevant communication tools depending on a scenario (e-mail; instant messaging; fax; video conference; face-to-face; voice conference; text message; printed media distribution; social media); determining the factors that affect communication tools (time zones/geographical factors language barriers; technical factors; cultural disparities; personal preferences; intraorganizational differences; interorganizational differences; relationship building; tailor method on the basis of message content; criticality factors; particular communication needs stakeholder). Additionally, the applicants should demonstrate their ability to determine most frequent communication triggers and define the target audience as well as rationale (risk register updates; milestones; schedule changes; project planning; project change; audits; task initiation/completion; stakeholder changes; gate reviews; business continuity response; response to incident; resource changes); utilize the following change control process within the context of a project depending on a scenario (change control process as well as common project changes types); determine organizational change types (outsourcing; process change; business merger/acquisition; relocation; business internal reorganization; business split).
  • Project Tools and Documentation (21%)Here the students need to prove that they are capable of comparing different project management tools (tools for performance measurement; software for project scheduling; charts; dashboard/status report; tools for knowledge management; SWOT analysis; consulted, responsible, informed, accountable RACI matrix); assessing project-centric documentation depending on a scenario (project management plan; project charter; scope statement; issues log; organizational chart; status report; communication plan; meeting agenda/meeting minutes; project schedule; dashboard information; section items); defining most frequent vendor-centric or partner documents as well as their function (mutually binding documents; request for proposal; request for information; request for quote).
  • Project Basics (36%)Within this objective, the test takers must have competencies in summing up the project properties (unique; temporary; start and finish; purpose; project as program component; project as portfolio component); categorizing project responsibilities & roles (project management office; champion/sponsor; project manager; project coordinator; stakeholder; scheduler; project team); compare and contrast standard project phases (initiation; planning; implementation; monitor and control; conclusion). Besides, the domain measures the examinees’ skills in defining the project cost control fundamentals (overall project cost; expense tracking; expense reporting; burn rate; budget); defining the most frequent structures of a project team organization (projectized; matrix; functional); implementing and developing project schedules depending on a scenario (work breakdown structure as well as scheduling activities); defining the Agile methodology basics (constant feedback; promptly adapt to new requirements; constant requirements gathering set a backlog iterative approach; burndown charts; sprint planning; SCRUM retrospective; daily SCRUM meetings/standup meetings; self-directed as well as self-organized teams); describing the value of personnel management, human resource & physical resource (resource management principles as well as personnel management).
  • Project Constraints (17%) This subject encompasses the following skills: predicting the impact of various constraint variables and influences throughout the project depending on a scenario (common constraints; influences); describing the importance risk strategies activities (strategies as well as risk activities).

>> CompTIA PK0-004 Online Training Materials <<

2023 CompTIA PK0-004 –Reliable Online Training Materials

Under the instruction of our PK0-004 exam torrent, you can finish the preparing period in a very short time and even pass the exam successful, thus helping you save lot of time and energy and be more productive with our CompTIA Project+ Certification Exam prep torrent. In fact the reason why we guarantee the high-efficient preparing time for you to make progress is mainly attributed to our marvelous organization of the content and layout which can make our customers well-focused and targeted during the learning process with our PK0-004 Test Braindumps.

CompTIA Project+ Certification Exam Sample Questions (Q170-Q175):

NEW QUESTION # 170
A customer has requested a change in an active project.
Which of the following actions should the project manager take FIRST?

  • A. Update the change log.
  • B. Inform the end user of the change.
  • C. Submit the change request to the project sponsor.
  • D. Gather input from the team.

Answer: C
NEW QUESTION # 171
While working on a project, a self-organized team determines what will be accomplished during the next two weeks.
Which of the following describes what the team is doing?

  • A. Creating a WBS
  • B. Holding a Scrum meeting
  • C. Gathering continuous requirements
  • D. Sprint planning

Answer: D Explanation:
A sprint, which is a time-bound period of work, always starts with a sprint planning meeting. During the meeting, team members choose items from the backlog to work on during the sprint. The backlog is a list of requirements (both functional and nonfunctional) for the project. The product owner prioritizes the backlog items based on business need, risk, and value to the organization. The Scrum team members break down large requirements into manageable portions of work that can be completed in a sprint.
NEW QUESTION # 172
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)

  • A. Project schedule
  • B. Scope management plan
  • C. Configuration management plan
  • D. Project plan
  • E. Network diagram

Answer: A,E Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,
Indianapolis, 2017, p. 171
NEW QUESTION # 173
A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST ?

  • A. In the beginning, projects entail a degree of uncertainty that needs to be specified.
  • B. In the beginning, projects have start and finish dates that require elaboration.
  • C. In the beginning, projects are part of a program that requires coordination.
  • D. In the beginning, projects start with detailed inputs that need to be explained.

Answer: A
NEW QUESTION # 174
A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?

  • A. Team Building
  • B. Team Selection
  • C. Resource loading
  • D. Resource leveling

Answer: A
NEW QUESTION # 175
...... With PK0-004 test guide, you only need a small bag to hold everything you need to learn. In order to make the learning time of the students more flexible, PK0-004 exam materials specially launched APP, PDF, and PC three modes. With the APP mode, you can download all the learning information to your mobile phone. In this way, whether you are in the subway, on the road, or even shopping, you can take out your mobile phone for review. PK0-004 study braindumps also offer a PDF mode that allows you to print the data onto paper so that you can take notes as you like and help you to memorize your knowledge. At the same time, regardless of which mode you use, PK0-004 test guide will never limit your download times and the number of concurrent users. For the same information, you can use it as many times as you want, and even use together with your friends. PK0-004 Latest Practice Questions: https://www.practicevce.com/CompTIA/PK0-004-practice-exam-dumps.html BONUS!!! Download part of PracticeVCE PK0-004 dumps for free: https://drive.google.com/open?id=1G8niZhzlguSDaBbbml9IHvXbkbhwyi2R